Here an article I found:https://www.elcorreogallego.es/sant...embre/idEdicion-2020-01-10/idNoticia-1222952/

"A "thousand per hour" for the Cathedral to be ready before December 31
Confidence that the works will finish before the start of the Holy Year // This month the restoration of the Main Chapel will begin

Operators and technicians try to optimize the time and resources to the maximum so that the works of the Cathedral are finished before the opening of the Holy Door, on December 31. Work is progressing as planned and deadlines are being met, as official sources of the Basilica say. Less than twelve months after the beginning of the Holy Year, the restoration project focuses on different areas of the great religious complex, both indoors and outdoors. The truth is that almost the entire structure, with the exception of the Obradoiro facade, already rehabilitated, is full of scaffolding and the machinery does not stop working.

On the one hand, the interiors are being recovered, where the works are already well advanced. The main nave is almost finished and you can see the result of the intervention at several points, especially in the vaults, where you can see the new white paint and also the delicate cleaning to which the granite elements were subjected. Likewise, the same sources point out, the south nave, which communicates with Platerias Square, is also almost finished, while technicians are now focusing on the north wing, that of the Immaculate Square; on the cruise, where the three arms of the Basilica converge; and also in the ambulatory, which surrounds the Main Chapel and where the Apostle's grave is located.

The restoration is being integral, that is, it includes, in addition to the three naves of the Basilica, some of the side chapels, such as the Cristo de Burgos. The work focuses on eliminating moisture from the vaults and the recovery of the vertical walls, where the mortars that were used in some of the actions of the twentieth century are removed, and to be covered; as well as sculptures or stained glass.

At the same time that these tasks are carried out, the restoration of the stone roofs is also being executed. In this sense, it should be remembered that one of the objectives of the Master Plan of the Cathedral is to end leaks and damp. Hence, it is essential to insulate the structure well before recovering the interiors.

The famous granite tile roofs are being rehabilitated while also replacing the tile roofs of the gyrola oratories. Precisely, a few days ago the intervention was completed in the Pilar Chapel, where on Wednesday the scaffolding began to be removed.

Work is also being done on the exterior façade of the cloister, which overlooks Platerias Square and the Fonseca Rua; as well as on the terrace, where a metal structure is also installed, and in the Treasure Tower. Cleaning and restoration work is being carried out on the surface. In addition, a new wooden structure is being executed and the roof covering is being renovated; as well as restoring the woodwork. Special elements such as Renaissance cresting, shields and medallions and Renaissance bars will also be arranged. They explain that in regard to the northern panda of the cloister, the works involve the lifting of the roof and the terrace that covers the whole for its renovation, making a wooden structure, a tile finish and a flat terrace with a finish of granite slabs

IMMINENT. From the Cathedral they indicate that the beginning of the restoration of the paintings of the Main Chapel is imminent. In this area, the tender for the recovery of the canopy, the reería, the silver altarpiece and the dressing room, where the seated Apostle who embrace thousands of people every year, is still pending. Everything indicates that the works in the paintings will begin "this same month", while with respect to the bidding and beginning of the set of gold and silver, it is expected that it will go out to the contest and work will begin in the first quarter of the year.

In the first three months of 2020, it is also estimated that the execution of the project of the facade of A Quintana and access to the Holy Door will be awarded and initiated. On the other hand, the start of the action on the steps of the Obradoiro facade is imminent, where the reería and the crypt will also be restored, a project financed by the Ministry of Development.
All interventions must be completed before the end of this year. That is the commitment of the Cathedral Foundation and also of the administrations and institutions involved in the restoration of SEO. Official sources of the Cabildo told this newspaper that the interior could be ready for Easter. In this context, the Xunta will allocate 800,000 euros this year, which adds up to the 17 million contributed by the State, so that everything is ready throughout 2020."
 

Wild Irish

Member
Camino(s) past & future
Mixed Camino/ Francés with variants (June/July 2021)
Here an article I found:https://www.elcorreogallego.es/sant...embre/idEdicion-2020-01-10/idNoticia-1222952/

"A "thousand per hour" for the Cathedral to be ready before December 31
Confidence that the works will finish before the start of the Holy Year // This month the restoration of the Main Chapel will begin

Operators and technicians try to optimize the time and resources to the maximum so that the works of the Cathedral are finished before the opening of the Holy Door, on December 31. Work is progressing as planned and deadlines are being met, as official sources of the Basilica say. Less than twelve months after the beginning of the Holy Year, the restoration project focuses on different areas of the great religious complex, both indoors and outdoors. The truth is that almost the entire structure, with the exception of the Obradoiro facade, already rehabilitated, is full of scaffolding and the machinery does not stop working.

On the one hand, the interiors are being recovered, where the works are already well advanced. The main nave is almost finished and you can see the result of the intervention at several points, especially in the vaults, where you can see the new white paint and also the delicate cleaning to which the granite elements were subjected. Likewise, the same sources point out, the south nave, which communicates with Platerias Square, is also almost finished, while technicians are now focusing on the north wing, that of the Immaculate Square; on the cruise, where the three arms of the Basilica converge; and also in the ambulatory, which surrounds the Main Chapel and where the Apostle's grave is located.

The restoration is being integral, that is, it includes, in addition to the three naves of the Basilica, some of the side chapels, such as the Cristo de Burgos. The work focuses on eliminating moisture from the vaults and the recovery of the vertical walls, where the mortars that were used in some of the actions of the twentieth century are removed, and to be covered; as well as sculptures or stained glass.

At the same time that these tasks are carried out, the restoration of the stone roofs is also being executed. In this sense, it should be remembered that one of the objectives of the Master Plan of the Cathedral is to end leaks and damp. Hence, it is essential to insulate the structure well before recovering the interiors.

The famous granite tile roofs are being rehabilitated while also replacing the tile roofs of the gyrola oratories. Precisely, a few days ago the intervention was completed in the Pilar Chapel, where on Wednesday the scaffolding began to be removed.

Work is also being done on the exterior façade of the cloister, which overlooks Platerias Square and the Fonseca Rua; as well as on the terrace, where a metal structure is also installed, and in the Treasure Tower. Cleaning and restoration work is being carried out on the surface. In addition, a new wooden structure is being executed and the roof covering is being renovated; as well as restoring the woodwork. Special elements such as Renaissance cresting, shields and medallions and Renaissance bars will also be arranged. They explain that in regard to the northern panda of the cloister, the works involve the lifting of the roof and the terrace that covers the whole for its renovation, making a wooden structure, a tile finish and a flat terrace with a finish of granite slabs

IMMINENT. From the Cathedral they indicate that the beginning of the restoration of the paintings of the Main Chapel is imminent. In this area, the tender for the recovery of the canopy, the reería, the silver altarpiece and the dressing room, where the seated Apostle who embrace thousands of people every year, is still pending. Everything indicates that the works in the paintings will begin "this same month", while with respect to the bidding and beginning of the set of gold and silver, it is expected that it will go out to the contest and work will begin in the first quarter of the year.

In the first three months of 2020, it is also estimated that the execution of the project of the facade of A Quintana and access to the Holy Door will be awarded and initiated. On the other hand, the start of the action on the steps of the Obradoiro facade is imminent, where the reería and the crypt will also be restored, a project financed by the Ministry of Development.
All interventions must be completed before the end of this year. That is the commitment of the Cathedral Foundation and also of the administrations and institutions involved in the restoration of SEO. Official sources of the Cabildo told this newspaper that the interior could be ready for Easter. In this context, the Xunta will allocate 800,000 euros this year, which adds up to the 17 million contributed by the State, so that everything is ready throughout 2020."
Thank you for this very detailed update 🙂👍
 

JabbaPapa

"True Pilgrim"
Camino(s) past & future
100 characters or fewer : see signature details
Thanks !!

Although this does mean that the work is now set to last 5-6 months longer than was originally hoped for.
 

ObeeOne

Member
Camino(s) past & future
Planning stage for 2020
Are they allowing pilgrims in? Has Mass returned to the Cathedral? If not, anyone know when it might be? Thanks.
 
Camino(s) past & future
First one in 1977 by train. Many since then by foot. Next one ASAP.
So: if I darken the Cathedral door sometime in late September or early October 2020, what can I expect?

I first visited the Cathedral in the summer of 1977 -- when one could still press one's hand into the 'holy handprint,' and all that.... My last visit was forty years later, in 2017.... I'd be very sorry to arrive in SdeC and not be able to visit my old friend.... The world, the flesh and the Devil being what they are, I cannot assume that I 'll get another chance.
 

SYates

Camino Fossil AD 1999, now living in Santiago de C
Camino(s) past & future
First: Camino Francés 1999
...
Last: Santiago - Muxia 2019

Now: http://egeria.house/
Are they allowing pilgrims in? Has Mass returned to the Cathedral? If not, anyone know when it might be? Thanks.
Yes, you can enter the cathedral, pray at the tomb and hug the apostle. There is no mass in the cathedral itself, but there is an 11:00 mass in the Corticela. For the rest, see the article linked/translated above ;-)
BC SY
 

SYates

Camino Fossil AD 1999, now living in Santiago de C
Camino(s) past & future
First: Camino Francés 1999
...
Last: Santiago - Muxia 2019

Now: http://egeria.house/
So: if I darken the Cathedral door sometime in late September or early October 2020, what can I expect?

I first visited the Cathedral in the summer of 1977 -- when one could still press one's hand into the 'holy handprint,' and all that.... My last visit was forty years later, in 2017.... I'd be very sorry to arrive in SdeC and not be able to visit my old friend.... The world, the flesh and the Devil being what they are, I cannot assume that I 'll get another chance.
Hopefully mass will be held in the cathedral by then again ;-) and so far you can always pray at the tomb. Also, remember, I hold the keys to Santa Susana and, with enough advance warning, you can celebrate mass there ;-)
BC SY
 

Get on our Mailing list for new products on the Camino Store and news from the Camino Forum








Advertisement

Booking.com

Camino Conversations

Camino Conversations

Forum Rules

Forum Rules

Forum Donation

Forum Donation
For those with no forum account, it is possible to donate here as well. Thank you for your support! Ivar

Follow Casa Ivar on Instagram

Most downloaded Resources

When is the best time to walk?

  • January

    Votes: 16 1.2%
  • February

    Votes: 10 0.8%
  • March

    Votes: 55 4.2%
  • April

    Votes: 197 15.0%
  • May

    Votes: 325 24.8%
  • June

    Votes: 95 7.3%
  • July

    Votes: 24 1.8%
  • August

    Votes: 27 2.1%
  • September

    Votes: 379 28.9%
  • October

    Votes: 158 12.1%
  • November

    Votes: 17 1.3%
  • December

    Votes: 7 0.5%

Camino Forum Store

Camino Forum Store
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock